Texas regulators have issued SpaceX an air permit for the gas-fired power plant at its planned data centre and supercomputer site in the Rio Grande Valley, Politico reports. Laura Lopez, a spokesperson for the Texas Commission on Environmental Quality (TCEQ), confirmed the permit was issued on Monday, US time. SpaceX didn’t respond to Politico’s request for comment.
The permit approves 35 gas-burning turbines producing 750 megawatts at the 444-acre site, according to a copy that the FracTracker Alliance obtained through a public records request and shared with Politico.

How the pause ended
On 21 September, Gov. Greg Abbott wrote to TCEQ with a directive “to pause the issuance of all permits related to data center projects until ERCOT completes its review.” ERCOT operates the Texas grid. TCEQ told him on 19 October that it had paused those permits.
On Friday, TCEQ received notice from Abbott’s office that ERCOT had finished gathering information on the potential community impacts of data centres, the Texas Tribune reports. Lopez told the Tribune: “The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations.” ERCOT plans to report its full findings to the Public Utility Commission on 10 December.

The project and the politics
Starbase’s city notice on 9 November put the project at about $24 billion for a gas-fired power plant and supercomputing facility, Reuters reports. SpaceX says the facility will generate its own electricity rather than draw from the public grid. The city’s commissioners meet on 9 December to consider tax abatements and a development agreement for the project.
Gina Hinojosa, who beat Abbott in the 3 November election, has pledged to keep data centre approvals paused until the Legislature passes new laws. She takes office on 19 January. Public Citizen called on TCEQ’s commissioners to resign after the resumption. “Texans are tired of this political theatre,” said Sam Law, a researcher at FracTracker Alliance. “We need real leadership, transparency, and a true moratorium on data center development.”

Abbott’s office and Hinojosa’s team didn’t immediately respond to the Tribune on Tuesday.